State regulators mark Madera subbasin groundwater plan “incomplete”

Water managers in the Madera subbasin will need to go back to the drawing board after the Department of Water Resources (DWR) marked the region’s groundwater plan “incomplete.”
A Nov. 19 letter from DWR states the Madera subbasin’s previously approved groundwater plan has now been deemed unsatisfactory as part of the agency’s periodic review of how plans are being implemented under the Sustainable Groundwater Management Act (SGMA).
The region’s seven groundwater sustainability agencies now have six months to make corrections. If those corrections aren’t acceptable, and the plan is deemed “inadequate,” the subbasin could be turned over to the Water Resources Control Board, SGMA’s enforcement arm.
The two main deficiencies cited by DWR are that agencies aren’t monitoring subsidence, or land sinking, where it’s happening and that state staff don’t believe the plan will get the region’s aquifers into balance by 2040, as mandated by SGMA.
“I would say I’m still reading the letter. I am a little disappointed, but know that subsidence is a growing edge for both DWR and the Madera Subbasin and that we’ll figure it out,” Madera County’s Director of Water and Natural Resources Stephanie Anagnoson told SJV Water.
Anagnoson referred to DWR’s newly released guidelines on dealing with subsidence.
Those new guidelines outline how agencies must manage aquifers to avoid further sinking caused by excessive groundwater pumping. Water managers are responsible for adding this new guideline to existing and lengthy groundwater plans.
Madera’s groundwater plan doesn’t adequately implement the new guidelines, Anagnoson said.
“That said, we always figure out a path forward. I don’t see anything in here that isn’t fixable,” Anagnoson said.
Madera is not alone.
Last month DWR deemed the Merced subbasin’s groundwater plan incomplete.
- SJV Water Reporter Allison Hunter contributed to this report